![]() ![]() ![]() Unmanned aerial vehicles (UAVs) also helped the construction team to take stock of the facility’s condition. The construction manager’s Virtual Design and Construction Group took the previous structural documents to create a base 3-D structural model so that BIM coordination could begin. Going paperless eliminated thousands of dollars in printing costs and hundreds of man-hours.īuilding information modeling (BIM) also played a substantial role in keeping the project moving forward while tracking its past. The entire 15-acre site was Wi-Fi-enabled, and project managers and subcontractors were assigned iPads, digital plan tables and Apple TVs so that when a project manager uploaded new drawings or requests for information, they were immediately downloaded onto each iPad in the field. Some of the regulatory changes included adding fire-stopping sealant for wall and floor penetrations, modifying existing doors to receive fire-resistant glass, replacing ceiling tiles, rerouting automatic door wiring, replacing regular outlets with ground fault circuit interrupter outlets and adding a primary disconnect at the transformer.īrasfield & Gorrie says it relied heavily on digital technology to rectify the project’s past with its present. On the 10th floor alone, the floor was core-drilled more than 500 times to reroute plumbing.Ī number of changes also were made to accommodate various code and standard updates that had occurred since the project’s original start date. The fifth floor originally was built as a general patient floor, but required a complete gutting to accommodate an intensive care unit and mechanical space as part of the new design. On the second floor, a 12-foot-thick concrete vault that was intended for a linear accelerator was demolished to make room for additional catheterization and electrophysiology procedure rooms. The original facility was designed as a rehabilitation hospital, but the new owners required a complete replacement facility, which meant that much of the previously completed work had to be demolished or renovated.Ī large portion of the first floor’s concrete slab was cut to reroute plumbing for the updated kitchen design. Photo courtesy of Grandview Medical Center ![]()
0 Comments
Leave a Reply. |
Details
AuthorWrite something about yourself. No need to be fancy, just an overview. ArchivesCategories |